Network maintenance - Math Building
Scheduled Maintenance Report for DoIT
Completed
The scheduled maintenance has been completed.
Posted Sep 11, 2019 - 08:30 EDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Sep 11, 2019 - 06:30 EDT
Scheduled
Network Maintenance schedule for the Math building.
Start date: September 11th
End Date: September 25th
Time: 6:30AM - 8:30AM

Networking is scheduled to perform network maintenance in the Math building. There will be a brief disruption of network services between 6:30 am and 8:30 am on each date and area listed below:

Wednesday, September 11th: 5th Floor Main IDF
Thursday, September 12th: 3rd & 4th Floor
Tuesday, September 17th: 1st and 2nd Floor
Wednesday, September 18th: PL Level
Thursday, September 19th: SL Level-Cola Lab
Thursday, September 26th: Main Math Core
Posted Sep 10, 2019 - 14:17 EDT
This scheduled maintenance affected: Network, Phones and TV (WolfieNet (Wi-Fi), Eduroam (Wi-Fi), Wired, Voice Over Internet Protocol (VoIP), Campus Television).